UPDATE
#MCDOT's Transportation Engineering contractors recently completed the following work on the MBT Phase 2 project:Drilled into Abutment B structure & installed rebar
Installed the formwork for Abutment B
Concrete will be poured soon (weather permitting)
Project Details https://www.montgomerycountymd.gov/dot-dte/projects/Metropolitan-Phase2A/index.html